AEC Contracts
Documentation | Arbitration | Expert Witness and Construction Law
Introduction
In any civil engineering project, given the fundamental importance of the
Contract Documents, it is often very important to minimise the pitfalls within
those documents that might potentially lead to contractual problems and disputes.
AEC members have prepared complete sets of contract documents for major projects
and through often bitter experience during both the writing and monitoring
of these contracts, have the engineering contract, financial and legal knowledge
required to attempt to minimise the potential pitfalls.
Given the best intentions of the author(s) of the Contract Documents for a
project, contractual problems and disputes often occur. AEC members have extensive
experience in all aspects of the resolution of contractual disputes, inclusive
writing claims reports on behalf of both clients, civil engineering consultants
and contractors, acting as Arbitrator's and as Expert Witnesses.
In particular, AEC members have particular experience of contractual disputes
in tunnels where variations in ground conditions are often the primary cause.
AEC members have written many claims on ground conditions in tunnelling projects
and members have acted as Expert Witnesses with respect to ground conditions,
spoil and tunnel lining. |
|
|
|
AEC members also have NEC Option C Target Works contracts
experience, this type of contract being used more commonly now, particularly
in tunnelling, where ground conditions are often unpredicable.
Contract Documentation
In any civil engineering project or contract it is only too easy inadvertently
to introduce a situation from which contractual problems and disputes are almost
inevitable. Often it is seen in hindsight that this situation arose even before
the Contract was made, because of pressures of time during preparation of the
Contract Documents. The experience of AEC is available to Employers who may
wish to minimise such problems.
Sometimes the Employer/Engineer side will prepare contract documents that
a tenderer may perceive as indicating that that side is attempting to obtain
an unduly advantageous position for itself at the outset. Such attempts to
gain an advantage before award of a contract can often rebound to the disadvantage
of that party due to some inconsistency that has been introduced. Consequently,
some contractors deliberately employ claims consultants whose first job is
to seek out such inconsistencies and develop claims for additional payment
from them. If inconsistencies were less common, this scenario would also be
less widespread. The problem arises at the Contract Document stage, where it
is very common indeed for printed contract conditions such as FIDIC to be "doctored",
and too often the result is conflicting clauses. There should be no surprise
if the Contractor is more claims-conscious than otherwise and appoints a claims
consultant to restore what he sees as a disadvantageous set of contract conditions.
At this point the battle for a smooth-running contract has already been lost.
Within AEC there is bitter experience of the scenario described above, and
the members of AEC are able to offer advice as to how best to allocate the
contractual risks fairly without such problems. Some members have prepared
complete sets of contract documents for several multi-contract hydro-electric
projects, and in doing so have encountered the need to consider very carefully
the matters set out above.
Defence projects including design of new technology are notorious for going
over budget. Concord is another example. If something is genuinely a new design,
the idea that its design development, production and construction/installation
can be priced for a fixed amount at the outset is very risky and it continues
to surprise practising engineers that the lesson is not learned by politicians
and financiers. A recent example is, of course, the Channel Tunnel, of which
AEC have direct experience. Again AEC can offer advice concerning the optimum
way of setting up a project.
The optimum printed Conditions of Contract must be selected. Later, there
can be insufficient coordination between the various people responsible for
drawing up the constituent parts of the Contract Documents, namely the Particular
Conditions of Contract, Specification, Method of Measurement and Bill of Quantities
(if used). Moreover, in the power generation sector in particular a very rigorous
approach to the coordination of civil and electrical/mechanical contracts,
together with efficient and strongly controlled arrangements for funding such
contracts, are imperative if interface problems and related claims are to be
avoided.
Construction Law
One AEC member is a construction specialist lawyer who has experience as a
construction specialist lawyer with major international contractors serving
the promoters of building, civil engineering, commercial development, defence,
mass transit, mechanical and electrical engineering, mining and nuclear power
projects. In addition, he has experience in the commercial, financing and contractual
aspects of project promotion, procurement, construction management and different
forms of resolving contentious issues gained within the multi - discipline
environment, including design and construct, of major construction groups and
public sector organisations on major projects of national and international
importance. He has advised clients seeking to contract, and contracting, in
Britain, Europe, North and South America, the Far East and Africa and on disputes
arising from such contracts.
Individual Members Experience
Many of our members have experience in Arbitration or have acted as an Expert
Witness. Please either check the individual cv's to find the appropriate experience
or contact us directly.
|